Details Project
Client
Kyaia
Scope
Engineering, Procurement and Construction (EPC)
Localization
Portugal
Implementation Time
30 Days
installed power
250 KW
Challenges //
Solutions
Kyaia was an ambitious project with a tight schedule combining latest technology for carpark implementation, and roof top particular conditions for structure assembly. CJR Solar had a dynamic team which is favorably overcome the challenge.
Projectscharacteristics
Solar panel
UP Solar 260 Wp Poly
Switchstation
15 kV Switchstation Upgrade Meters meters
>
What we did
// Cable Trenches and ducts
// Foundations
// Supply and Installation of solar Panels
// Supply and Installation of inverters
// Supply and Installation of Structures (roof top & carpark) Monitoring System
// Tests and commissioning & Grid Connection